Friday, 31 August 2012

The foundations are nearly complete, and we are well on the way with substructure masonry works.  The precast concrete lift shaft has also been delivered to site which we are hoping to have installed week commencing 3rd September 2012.



Friday, 17 August 2012

Foundations are ongoing to area B and C.  Sub-structure block work has started to lower area of A, and completion of the bulk excavation ...!!

Works for next week include gas membrane installation for the two lift shafts, and concrete continue with foundations and sub-structure block work.

Friday, 3 August 2012

This week we completed the 90% of the bulk shift operation, and started to pour the foundations...