Continuing on from last week, the floor insulation is now fully complete along with the screed. There has been a massive change to section A as the ground floor timber frame has been fixed into place. The transport road running around the back of the site for assess and egress has been laid and is complete. Also, the external drainage is 90% complete and ready to tarmac.
Friday, 26 October 2012
Friday, 19 October 2012
At the beginning of the week, two major sections of the concrete screed was poured. Whilst the screed was taking shape, continuous facing brickwork was progressing round the perimeter of the building, followed closely by the scaffolding. Insulation is also nearly complete with 90% of the works already fitted. As the week comes to a close, the timber frame has commenced to section A with the soleplates being laid and the first couple of panels being fixed.
Wednesday, 17 October 2012