Friday, 19 October 2012

At the beginning of the week, two major sections of the concrete screed was poured. Whilst the screed was taking shape, continuous facing brickwork was progressing round the perimeter of the building, followed closely by the scaffolding. Insulation is also nearly complete with 90% of the works already fitted. As the week comes to a close, the timber frame has commenced to section A with the soleplates being laid and the first couple of panels being fixed.