Friday, 25 January 2013

Progress has been limited this week due to the inclement weather. The timber frame has been progressing slowly whilst the dry lining contractor has been carrying out works in selected plots which have not been affected by the snow. Looking forward into next week, we hope the snow clears up and allows a big push in production for numerous trades.



Friday, 18 January 2013

Even with the adverse weather conditions , progress of works has still carried on with numerous trades battling through the elements. As seen in the pictures, ceiling insulation and plasterboard has now started to the flats. The UPVC windows are mostly installed to Area B and the screed has just been poured to the section where the crane was originally positioned.

 

Friday, 11 January 2013

There has been a huge push in production with various different trades since our Considerate Constructors visit in December  especially with the transformation of the roof to Areas A and B which is partly tiled and loaded out.  The windows are also nearly complete to area A and the plasterers  and electricians will commence on site on Monday 14th December. Render to the gable ends of area A has begun and will continue in to next week.  The soleplates to area C are being laid with the ground floor panels arriving on Wednesday 16th January.