There has been a huge push in production with various different trades since our Considerate Constructors visit in December especially with the transformation of the roof to Areas A and B which is partly tiled and loaded out. The windows are also nearly complete to area A and the plasterers and electricians will commence on site on Monday 14th December. Render to the gable ends of area A has begun and will continue in to next week. The soleplates to area C are being laid with the ground floor panels arriving on Wednesday 16th January.