Monday, 18 March 2013

We are currently very busy on site with many trades progressing with their works rapidly throughout the building. As seen within the photo, the atrium to section B is ready to be glazed and is looking excellent. Mechanical and Electrical works first fix is also well on its way throughout section A.


In other News!

Frank Johnson, as mentioned in last week’s blog is holding an event in Wakefield for Charity. Poster below !


Friday, 1 March 2013

Following on from a very productive week we have started to form the flat roofs to area C which is shown in the photos. Also our labourer/cleaner Frank Johnson is currently raising money for Cancer Research UK. We have had  the charity box in the office and we hope to raise some money for this good cause. We also have installed our Hardhat Media information screens which give Health and Safety bulletins and general information to the operatives within the cabin.