Friday, 23 November 2012

We have further progressed the timber frame to areas A and B whilst battling against the elements from the wind and rain! Rooms are now starting to take shape whilst the roof is ready for coverings to the bottom of area A. The scaffolding is moving rapidly around the perimeter of the building as well as loading bays being formed to the designated areas.
Kingfisher Windows recently started on Monday 19th November and are now forming windows around the ground floor of area A.




Monday, 12 November 2012

As O’Donnell Civil engineers begin to pack up their bags after finishing their first successful visit, Lowfield Timber Frame are getting firmly stuck in with the erection of the timber frame to section A and B. The brick layers are also progressing well with the substructure around the perimeter and the scaffold is also taking shape.




Friday, 2 November 2012

The First Floor Cassettes of the Timber Frame are now being fixed to Area A. Further progression can now be seen in the masonry work which is now coming up to finished floor level.